EMT Practice Test
1. Question Content...
Question2: How many people are there in a team of Developers?
Question3: When is it allowed for a Scrum Master to cancel a Sprint?
Question4: A self-managing Scrum Team can decide to stop doing Daily Scrums.
Question5: Each Sprint can be considered a short project following Scrum.
Question6: Which of the following statements are correct about "technical debt"?
Question7: The Sprint Goal is created during the Sprint Review and then added to the Sprint Backlog.
Question8: In the Daily Scrum, the Scrum Master is not allowed to attend.
Question10: Why are Sprints fixed length events of one month or less?
Question11: What should happen between two Sprints following Scrum?
Question12: Revenue is the only measure of product's value.
Question13: A new Sprint starts immediately after the conclusion of the previous Sprint.
Question14: In the Daily Scrum, the Product Owner is not allowed to attend.
Question15: Which statement about the size of the Development team ("Developers") is correct.
Question17: What is the main reason for the Product Owner to be part of the Daily Scrum?
Question18: Which of the following best describes the Scrum Pillar "Transparency"?
Question19: What is the main role of a QA in Scrum?
Question22: When is the Sprint Goal crafted by the Scrum Team?
Question23: What happens with "Done" Sprint Backlog items when a Sprint was cancelled?
Question25: Which of the following should a Scrum Master do to start a project?
Question27: Why do we need a Sprint Goal in Scrum?
Question29: What kind of testing should be done during the Sprint?
Question30: Sprints are fixed length events of one month or less to create consistency.
Question32: Which two of the following are not correct about non-functional requirements?
Question35: The Product Backlog has to be completed before the Sprint 0 can start.
Question36: The Product Owner is accountable for effective Product Backlog management.
Question37: Each artifact contains a commitment. For the Sprint Backlog it is the Sprint Goal.
Question38: Each artifact contains a commitment. For the Sprint Backlog, it is the:
Question39: The length of a Sprint should be:
Question41: The Sprint Goal must be finalized prior to the end of Sprint Planning.
Question42: Which statement is correct about the Sprint Backlog?
Question44: Which of the following are accountabilities of a Scrum Team?
Question45: What is the time box for the Daily Scrum?
Question46: Which of the following answers is mandatory in Scrum?
Question48: The Developers can change the Sprint scope on their own as more is learned.
Question49: The 3 Pillars of Scrum are creativity, inspection and adaptation.
Question51: Sprint Review is not a formal meeting.
Question52: When should testing tasks be done?
Question53: The satisfaction of which stakeholder is the most important?
Question54: When is a Sprint over according to Scrum?
Question58: Within a Scrum Team, there are no sub-teams or hierarchies.
Question60: A Scrum Team typically consists of 10 or fewer people.
Question61: The Definition of Ready is defined by the Product Owner.
Question62: Which statements about the Product Backlog are correct?
Question63: Does a new Sprint always start immediately after the conclusion of the previous Sprint?
Question64: The Product Owner is responsible to define the Definition of Ready.
Question65: What should the Developers do when they realize that the Sprint scope should be changed?
Question67: A good Scrum Team has at least one Design Sprint every year.
Question68: Scrum events are designed to enable the transparency required.
Question70: What is the main accountability (roles = outdated term) of a Project Manager in Scrum?
Question72: Scrum is founded on empiricism and lean thinking.
Question73: What is the time box for the Sprint Review meeting?
Question79: The Developers are responsible for inspecting the progress toward the Sprint Goal.
Question81: The Product Backlog is baselined before the Sprint 0.
Question82: In each Sprint Backlog at least one high priority process improvement items is existing.
Question84: Only the Product Owner can cancel a Sprint.
Question85: The Sprint Review is an opportunity for inspecting and adapting in Scrum?
Question86: In the Daily Scrum, the Developers are allowed to adjust their plan for the Sprint.
Question87: The Developers are accountable for ordering Product Backlog items.
Question88: Which of the following actions may a Scrum Master take in starting up a project?
Question89: Which of the following actions should a Scrum Master do to start a new Project?
Question90: What test types should be done during the Sprint?
Question91: What is the time box for the Sprint Retrospective meeting?
Question92: Each artifact contains a commitment. For the Increment it is the Definition of Done.
Question93: Only the Developers are influencing the Definition of Done, no one else.
Question95: Which Scrum accountability (role = outdated term) is owning the Sprint Backlog?
Question97: When can a Sprint be cancelled?
Question98: The commitment contained in the Product Backlog is:
Question99: Which practices are allowed to forecast the Sprint progress following Scrum?
Question101: What is the time box for a Sprint?
Question103: Which of the following is a measure of success for the project?
Question104: Which statement explain when a Product Backlog item is considered "Done"?
Question105: Which answer best describes Scrum?
Question108: What does it mean for a team to be a "cross-functional" Team?
Question109: The Sprint Goal is the single objective for the Sprint.
Question110: Self-management means, that the team can decide which Scrum events are needed.
Question111: The Scrum Master in a Scrum Team is responsible for creating a plan for the Sprint.
Question114: A baselined Product Backlog is called?
Question115: When does a new Sprint start?
Question116: Why are smaller teams better, following Scrum?
Question117: Multiple Scrum Teams working on the same product must have the same Sprint start/end.
Question118: To double the Developers will double the productivity.
Question119: The Product Owner ist allowed to participate in the Daily Scrum if:
Question120: Who is responsible for tracking the progress in a Sprint?
Question121: The Product Owner is not part of the Scrum Team.
Question123: The Scrum Master is accountable for establishing Scrum as defined in the Scrum Guide.
Question125: Is it allowed that the Scrum Master attends the Daily Scrum?
Question128: Is it allowed to forcast the Sprint progress using burn-down charts, following Scrum?
Question129: Which of the following answers limits "work in progress"?
Question130: When a Sprint is cancelled - what happens to the "done" Sprint Backlog items?
Question131: The Product Backlog is the single source of work undertaken by the Scrum Team.
Question133: Scrum can be used to create new products, not to sustain or renew products.
Question134: What is Velocity?
Question135: Based on which criteria should the Product Owner order the Product Backlog items?
Question136: The Sprint Review should be held at the same time and place to reduce complexity.
Question138: The Product Owner can also be a member of a team of developers.
Question139: The Product Owner can allow the Developers to create items for the Product Backlog.
Question140: Each artifact contains a commitment. For the Product Backlog it is the Product Goal.
Question142: What happens usually between a Sprint Retrospective and the next Sprint Planning?
Question143: The Sprint Retrospective meeting is a time boxed Scrum event.
Question144: Product Backlog refinements are not required in Scrum.
Question145: Which statement is true about the Product Backlog?
Question146: Which of the following is needed for starting a new Sprint Planning?
Question149: The Sprint length can be 3 weeks.
Question152: The Sprint Review is a working session.
Question153: The Scrum Master is not important anymore if teams are self-managed.
Question154: It is allowed to change the scope during a Sprint.
Question155: What three specific accountabilities does Scrum define within the Scrum Team?
Question156: What does a burn-down chart measure in a project?
Question158: The Scrum Values are: commitment, courage, focus, openness, and maximizing value.
Question162: The Scrum Values are: commitment, courage, creativity, openness, and respect.
Question163: Which of the following are mandatory in Scrum?
Question164: A good Scrum Team has at least one Release Sprint every year.
Question165: The Sprint Planning meeting is a time boxed Scrum event.
Question166: Which of the following should not be changed during a Sprint?
Question167: Which statement about the Product Backlog is correct?
Question170: How many developers are in a scrum team?